Microsoft Managing Projects with Microsoft Project 2013 - 074-343 Exam Practice Test

You are using Project Standard 2013.
You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field.
What should you do?

Correct Answer: C Vote an answer
You are using Project Standard 2013.
Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.
You need to show one line item that displays all the requested information in the Gantt view.
What should you do?

Correct Answer: D Vote an answer
DRAG DROP
Your company uses Project Professional 2013.
You are a program manager in charge of a multi-program software integration project. The project is scheduled from January 1, 2012-August 3, 2013. You have a consultant resource that charges a different rate based on each task completed. Tasks 1 through 9 are billed at a rate of $150.00 per hour. Tasks 10 through 20 are billed at a rate of $175.00 per hour.
You need to set up your schedule to ensure that the correct resource rate is associated with the correct tasks.
Which two actions should you perform in sequence? (To answer, move the appropriate two actions from the list of actions to the answer area and arrange them in the correct order.)
Correct Answer:

Explanation:
Box 1:

Box 2:

Note:
You can model these more complex billing schemes by using rate-table features in Project:
References:
You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?

Correct Answer: B Vote an answer
You are a project manager who uses Project Professional 2013.
You work in a software development project, which is in progress and has reached 60% of actual progress. Your company decides to use the new Project Reports views to communicate all the project progress across the key users. They also decide to report information about a specific period only, normally one month behind the current day.
You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?

Correct Answer: A Vote an answer
You are a Project Manager who uses Project Professional 2013.
You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.
One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.
What should you do?

Correct Answer: C Vote an answer
Your organization uses Project Professional 2013.
A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost.
You write a formula to display the indicator, but it only displays for normal tasks and not for summary tasks.
You need to make the indicator display for summary tasks.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

Correct Answer: C,D Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어