Microsoft Managing Programs and Projects with Project Server 2013 - 074-344 Exam Practice Test

You are a portfolio manager for an organization that uses Project Server 2013.
You plan to create several portfolio reports for the executive team.
You need to ensure that your first report shows a list of all projects in your organization with
timephased information regarding how the Actual Work and the Actual Cost have varied on
a monthly basis.
What should you do?

Correct Answer: D Vote an answer
You are a project manager for an organization that uses Project Server 2013. One enterprise project has grown in complexity and size; the project manager creates sub-sites to organize the work by team.
All the teams are comfortable working with a familiar tool, such as the Microsoft SharePoint site. However, management cannot view all of the work being performed in the portfolio, and they need to permanently make decisions about the best use of the resources.
You need to bring all of this work into visibility in the least amount of time and without affecting current resource processes. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

Correct Answer: C,D Vote an answer
You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool.
After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change.
You need to solve this problem.
What should you do?

Correct Answer: A Vote an answer
Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Correct Answer: A,B,C Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
You are a project manager for an organization that uses Project Server 2013.
You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules.
You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks.
What should you do?

Correct Answer: C Vote an answer
The IT department uses Project Online services to analyze the projects they will execute the next year. Four projects in the pool with their respective priority and costs are shown in the exhibit. (Click the Exhibit button.)

The team wants to get the most value from their portfolio, with the cost constraint indicated.
There are some last-minute restrictions that could change their selection; the CEO indicates that the CRM Global Training project must occur when the CRM Deployment Project takes place.
As the portfolio analyzer, you need to assist the team in achieving their goals.
You force-in the CRM Global Training project. What are two results of this action? (Each correct answer presents part of the solution. Choose two.)

Correct Answer: C,D Vote an answer
You are a project manager who uses Project Online.
You build and publish a resource plan for your project. You check the resource demand in the Resource Availability screen.
You do not see the correct demand as defined in the resource plan.
You need to see the correct demand.
What should you do?

Correct Answer: D Vote an answer
You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and selection process.
Your project is now selected for detailed planning. You complete a detailed work breakdown structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?

Correct Answer: E Vote an answer
DRAG DROP
You work as a team member for an organization that uses Project Server 2013.
The organization tracks work in hours and has single-entry mode enabled. You are required to complete a timesheet at the end of each week. For this week's timesheet, you only have one assigned task to complete.
You need to ensure that your timesheet is accurate and ready for approval.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
Correct Answer:
You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?

Correct Answer: C Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어