Oracle Primavera P6 2021 Enterprise Project Portfolio Management - 1Z0-129 Exam Practice Test

An activity is to be completed within a fixed time period and the total amount of work is fixed. What duration type should be used?

Correct Answer: D Vote an answer
You are a project manager managing a large construction project. One of the pieces of heavy equipment required to dig the Foundation will most likely not be available until a specific date, because that equipment has been allocated to another, higher priority project. In that related project schedule you clearly see that in all likelihood, the activity in that plan that uses that equipment will also slip. You want to reflect this in your project schedule using a constraint. What would be the most appropriate constraint to use?

Correct Answer: C Vote an answer
You are working in a project plan that has been baselined multiple times. Each of the baselined reflects expected effort for three different sets of defined scope. After reviewing the plan, management has decided that a previous baseline/scope definition will be used going forward. Which action should be executed in the Client?

Correct Answer: C Vote an answer
You are an application administrator. You have been asked by your CEO to simplify the user interface for executives like her who are interested in high level summary information. Identify two ways to satisfy this request.

Correct Answer: A,C Vote an answer
Calculated Project User Defined Fields and .

Correct Answer: D,E Vote an answer
Identify the impact of deleting a resource from the Resource Breakdown Structure?

Correct Answer: A Vote an answer
Identify the true statement.

Correct Answer: D Vote an answer
Identify the true statement regarding administrative functions in P6 R8.

Correct Answer: B Vote an answer
Select the true statement regarding Project level Security Profiles.

Correct Answer: B Vote an answer
You are developing a reporting strategy for a customer who requires monthly reports showing cost variance. The customer has two requirements.
1. Each report must come from Primaver
a.
2. Each month''s report must become a "snapshot" for legal traceability purposes. Which P6 R8 solution addresses each of the customer''s requirements?

Correct Answer: D Vote an answer
You are a Resource Manager making resource assignments in P6 EPPM Web Plan Resources view. You can clearly see that the changes have been made. You move to another section of P6 EPPM Web, and return to the Plan Resources view, only to find that your changes have not been retained. What is the likely cause of this problem?

Correct Answer: D Vote an answer
What is the significance of the setting "Summarize project based on detailed activity resource assignments"?

Correct Answer: C Vote an answer
Identify the business case that would support the creation of OBS elements to align with WBS elements within individual project plans.

Correct Answer: D Vote an answer
Identify the TRUE statement regarding Work Breakdown Structures (WBS).

Correct Answer: B Vote an answer
Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.

Correct Answer: D Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어