Oracle Manufacturing Cloud 2018 Implementation Essentials - 1Z1-1002 Exam Practice Test
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
Correct Answer: E
Vote an answer
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items with some overlap between them in terms of products manufactured. The distribution centers stock parts from all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team defines the items and sets the attributes for most parameters. The respective distribution centers and manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.
Identify two different ways of achieving this requirement.
Correct Answer: B,C
Vote an answer
Identify the two capabilities that the Application Development Framework Desktop Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.
Correct Answer: A,C
Vote an answer
Identify the three sources from which supply chain orchestration (SCO) can create the work orders.
Correct Answer: B,C,D
Vote an answer
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
Correct Answer: D
Vote an answer
To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.
Identify the action that meets this requirement.
Correct Answer: B
Vote an answer
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
Determine the available capacity of the resource R1 for that week.