Oracle Project Management Cloud 2024 Implementation Professional - 1z0-1057-24 Exam Practice Test
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
Correct Answer: A,D
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes
/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
Correct Answer: A,D
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which data format is supported by SOAP Web services to establish communication between web services consumers and web services providers?
Correct Answer: C
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice.
After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
Correct Answer: A
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
Correct Answer: B
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?
Correct Answer: A
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?
Correct Answer: A
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
Correct Answer: B,C
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).