You are in the screening phase of a Proactive Maintenance (4HI) process. What is the correct sequence of the next three process steps?

Correct Answer: B Vote an answer
You schedule a time-based single cycle plan with the following assigned planning data:
* Start date for Scheduling: 01.07.2023
* Scheduling indicator: Time
* Call Horizon: 20%
* Cycle Modification Factor: 2
* Cycle/Unit: 10 DAY
What is the resulting call date?

Correct Answer: C Vote an answer
Where can you assign a maintenance work center? Note: There are 2 correct answers to this question.

Correct Answer: A,B Vote an answer
As a Maintenance Planner you have set the status of the maintenance order with actual costs to Technically Complete (TECO).
What actions can you perform on the maintenance order in TECO status?
Note: There are 3 correct answers to this question.

Correct Answer: B,C,D Vote an answer
In what phase of the SAP Activate methodology do you test the business processes?

Correct Answer: D Vote an answer
Which tasks can be performed by a Maintenance Technician role in the Reactive Maintenance process? Note: There are 3 correct answers to this question

Correct Answer: A,B,C Vote an answer
Which of the following features apply to the new scope items (4HH, 4HL, 4VT and 4WM)? Note: There are 2 correct answers to this question.

Correct Answer: A,D Vote an answer
Which tool do you use to develop your own cloud applications for SAP S/4 HANA Cloud?

Correct Answer: D Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어