SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 - C-TSCM42-66 Exam Practice Test

You want to enhance the system statuses of a production order with user statuses.
How do you do this?

Correct Answer: D Vote an answer
In SAP ECC, you calculate the standard available capacity for a work center capacity using the followingdata:
-Start: 7:00:00 a.m. -End:3:00:00 p.m.
-Break duration: 1 hour
-Rate of utilization: 80% -Overload:110%
-Number of individual capacities: 1
How large is the standard available capacity?

Correct Answer: C Vote an answer
Which of the following master data is necessary for the creation of material reservations for production orders?

Correct Answer: C Vote an answer
In which scenario will the error message shown in the attached screenshot occur? Exhibit:

Correct Answer: C Vote an answer
What do you have to consider, when you use the ATP (Available To Promise) checks for material?(Choose two)

Correct Answer: C,E Vote an answer
You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC?(Choose two)

Correct Answer: B,C Vote an answer
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

Correct Answer: B Vote an answer
What could be a consequence of confirming an operation?

Correct Answer: C Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어