A Power Systems server has two HMCs connected to its Flexible Service Processor (FSP). It is decided to upgrade one of them to a later hardware version. The 7042-CR3 is disconnected and the new 7042-CR6 is connected in its place. The new HMC successfully discovers the managed server but some operations including DLPAR are failing.
Which action will allow the managed server and HMC to establish new RMC configurations?
Which action will allow the managed server and HMC to establish new RMC configurations?
Correct Answer: A
Vote an answer
A customer is planning to migrate an existing AIX 7 environment from POWER5 hardware to POWER7. The existing deployment consists of multiple machines, each hosting many LPARs. Due to software licensing constraints, the new environment must maintain the same number of logical CPUs. The pmcycles command reports the following on an LPAR on the POWER5 environment:
$ pmcycles -m CPU 0 runs at 2198 MHz CPU 1 runs at 2198 MHz CPU 2 runs at 2198 MHz CPU 3 runs at 2198 MHz CPU 4 runs at 2198 MHz CPU 5 runs at 2198 MHz CPU 6 runs at 2198 MHz CPU 7 runs at 2198 MHz
How many virtual CPUs should be assigned to the destination LPAR on the POWER7 environment?
$ pmcycles -m CPU 0 runs at 2198 MHz CPU 1 runs at 2198 MHz CPU 2 runs at 2198 MHz CPU 3 runs at 2198 MHz CPU 4 runs at 2198 MHz CPU 5 runs at 2198 MHz CPU 6 runs at 2198 MHz CPU 7 runs at 2198 MHz
How many virtual CPUs should be assigned to the destination LPAR on the POWER7 environment?
Correct Answer: A
Vote an answer
An administrator is planning to configure two new Power Systems servers for Live Partition Mobility (LPM). Each server will be connected to a separate HMC. What is required to achieve this in addition to those requirements needed for LPM with a common HMC?
Correct Answer: B
Vote an answer
Which of the following statements is true when considering Active Memory Sharing?
Correct Answer: A
Vote an answer
A system administrator needs to configure a redundant network environment for several AIX and Linux clients on a Power Systems server. Which highly available Virtual I/O server network solution should be used to meet this requirement?
Correct Answer: A
Vote an answer
An architect has been given the task of incorporating some new Power Systems servers running AIX 7 into an existing data center which is supported by a legacy SAN.
The new servers will need to be connected to the SAN, and the LPARs on the servers will each have access to a Fibre Channel Tape using virtualized devices.
Which action will the architect need to take?
The new servers will need to be connected to the SAN, and the LPARs on the servers will each have access to a Fibre Channel Tape using virtualized devices.
Which action will the architect need to take?
Correct Answer: D
Vote an answer
How can SMT be temporarily disabled at the next boot of a Linux LPAR?
Correct Answer: B
Vote an answer
A number of uncapped partitions, which do not use multiple shared processor pools, are requesting additional processor resources. There are not enough resources available to satisfy all the requests. How does the hypervisor determine allocation of the available resources?
Correct Answer: B
Vote an answer
When attempting to install a VIO client using NIM, an adminstrator finds that no disks are available for installation. The disks are provided by NPIV through the virtual Fibre Channel adapter as described here:

Which of the following explains why is the administrator unable to see the disks?

Which of the following explains why is the administrator unable to see the disks?
Correct Answer: B
Vote an answer
An administrator has an existing NIM server running AIX 5.3 TL9. They would like to use this NIM server to upgrade an existing VIO server (VIOS) partition from version 1.5 to version 2.2 FP24.
Correct Answer: B
Vote an answer