SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 - C_TS422_2021 Exam Practice Test
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
Correct Answer: A
Vote an answer
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?
Correct Answer: A
Vote an answer
You are working with planning strategy 40 (Planning-with-final assembly) When does consuption of planned independent requirements take places?
Correct Answer: B
Vote an answer
How can you set up the supply source for the Kanban process in SAP S/4HANA?
Correct Answer: A,B,C
Vote an answer
You want to set up a make-to-order planing scenario for finished material. The bil of material contains two components: one should be procured for each sales order individually, the other one shold be procured jointly for all independent requirements. Forcasting for the finished product is NOT possible. Which setting do you make to achive this?
Correct Answer: A
Vote an answer
What are the consequences if the Dispatched operation status is set for a production order operation?
Correct Answer: A,C
Vote an answer
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
Correct Answer: D
Vote an answer
What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?
Correct Answer: A
Vote an answer