SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 - C_TSCM42_66 Exam Practice Test

Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?

Correct Answer: B Vote an answer
In what sequence are the steps of material requirements planning performed in SAP ECC?

Correct Answer: A Vote an answer
Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned
orders?(Choose three)

Correct Answer: A,B,D Vote an answer
What do you have to consider regarding ATP checks in SAP ECC that are triggered from customer orders?

Correct Answer: A Vote an answer
What do you have to consider when you use SAP ECC long-term planning (LTP)?(Choose two)

Correct Answer: B,C Vote an answer
Which of the following scheduling types can only be used in capacity planning?

Correct Answer: C Vote an answer
In SAP ECC, you calculate the standard available capacity for a work center capacity using the followingdata:
-Start: 7:00:00 a.m. -End:3:00:00 p.m.
-Break duration: 1 hour
-Rate of utilization: 80% -Overload:110%
-Number of individual capacities: 1
How large is the standard available capacity?

Correct Answer: C Vote an answer
An enterprise based in the US produces an end product that is used with the unit of measure "pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit "kilogram" (KG).
What is the easiest way to fulfill this requirement?

Correct Answer: C Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어