Microsoft Dynamics AX 2012 R2 Project - MB6-700 Exam Practice Test
You need to generate a report to analyze the costs and revenues by project for a specified date range.
Which report should you select?
Which report should you select?
Correct Answer: B
Vote an answer
You assign resources to a project quotation with a work breakdown structure.
Competencies are used to determine which resources are appropriate for assignment.
On which entity are competencies set?
Competencies are used to determine which resources are appropriate for assignment.
On which entity are competencies set?
Correct Answer: D
Vote an answer
You set up a new internal project that includes work in process (WIP).
You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet.
Which form should you use to specify that each type of cost will be posted to balance accounts?
You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet.
Which form should you use to specify that each type of cost will be posted to balance accounts?
Correct Answer: B
Vote an answer
You work with a fixed-price project.
To which process do the completed contract and completed percentage assessment
principles relate?
To which process do the completed contract and completed percentage assessment
principles relate?
Correct Answer: D
Vote an answer
Which two tools enable you to control a project? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,C
Vote an answer
You use the progress billing rule to invoice a project. Which action can be performed automatically by Microsoft Dynamics AX?
Correct Answer: B
Vote an answer