PMI Risk Management Professional - PMI-RMP Exam Practice Test

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed?
(Choose two.)

Correct Answer: A,D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.
What should the risk manager do next to understand the differences between planning and execution?

Correct Answer: A Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
The customer expresses concern about the increasing likelihood of delays from one of the subcontractors on the project. This risk was previously identified and planned for during the project planning phase. The project sponsor reassured the customer that this is a known risk and will be handled accordingly by the risk manager.
What should the risk manager do?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.
Which tool could the risk manager use to discover the project risk categories?

Correct Answer: C Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.
Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Correct Answer: B,C,E Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.
What will be the main output of this meeting?

Correct Answer: A Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment What should the risk manager do?

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어