An 8 AWG bare copper equipment ground conductor (EGC) is wire tied to the module mounting structure of a commercial rooftop solar array. After a few years of operation, some spots on the EGCbegin to turn a green color and appear to be corroding more significantly that other places. What would the MOST likely cause of the problem?
Correct Answer: C
Vote an answer
A bifacial PV module has a rated power of 350W on the front side and a bifaciality factor of 70%. If the rear side receives 200 W/m² of irradiance, what is the total power output under STC front-side conditions (1000 W
/m²)?
/m²)?
Correct Answer: C
Vote an answer
A PV connection is being made at the center of a 300 ft. long 200 feeder. See the attack diagram. The feeder originates in the upper third of the 800A main service panel (800A main breaker) with a 200A breaker and terminates in a 200A main-lug-only subpanel. The rated output of the PV system inverter is 100A.

Which are the NIMUMUM actions required to achieve an NEC-compliant installation?

Which are the NIMUMUM actions required to achieve an NEC-compliant installation?
Correct Answer: A
Vote an answer
A ground-mount PV system is planned for a site with a soil bearing capacity of 2000 psf. The array footing design requires a minimum bearing pressure of 1500 psf. What is the safety factor for this installation?
Correct Answer: A
Vote an answer
Which circuits are on the utility side of a service point?
Correct Answer: B
Vote an answer
On a PV system larger than 100kw, which PV array design will provide the HIGHEST degree of performance monitoring.
Granularity, and ease of troubleshooting performance issues?
Granularity, and ease of troubleshooting performance issues?
Correct Answer: A
Vote an answer
A PV system requires labeling per NEC 690.56. Which of the following must be posted at the point of interconnection?
Correct Answer: B
Vote an answer
A PV system was installed in July 2017 under the 2017 NEC. The system has a string inverter located inside a garage on a wall 10 ft, from the outside wall and 1oft, from the ac load center at the point of utility connection. The PV system has a PV array on the roof. Which of the following represents the PV rapid shutdown system requirement for the controlled PV system conductors associated with this PV array?
Correct Answer: C
Vote an answer
A module's Voc is 40V at STC. At -5°C with a coefficient of -0.33%/°C, what is the Voc?
Correct Answer: B
Vote an answer
A PV system's capacity factor is 18%. The array is 10 kW, and it operates 365 days/year. What is the annual energy output?
Correct Answer: B