Question #: 97
Topic #: 5
Question #: 97
Topic #: 5
For an item with high profit impact and low supply risk, what would be a likely procurement strategy to support the overall supply strategy?
Suggested Answer: C Vote an answer
For items with high profit impact and low supply risk, the recommended procurement strategy is to exploit purchasing power and minimize cost. This approach involves negotiating favorable terms with suppliers, leveraging volume discounts, and seeking cost reductions to maximize profitability. Since the supply risk is low, the focus can be on optimizing costs without significant concern for supply disruptions. Options A, B, and D are appropriate for different supply risk and profit impact scenarios but do not align with the characteristics described.
References:
* Kraljic, P. (1983). Purchasing Must Become Supply Management. Harvard Business Review.
* https://www.cips.org/knowledge/procurement-topics-and-skills/strategy-policy/models/kraljic-matrix/
References:
* Kraljic, P. (1983). Purchasing Must Become Supply Management. Harvard Business Review.
* https://www.cips.org/knowledge/procurement-topics-and-skills/strategy-policy/models/kraljic-matrix/
by Harlan at Jun 29, 2026, 07:08 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).