FL uses an absorption costing system. The overhead absorption rate for production overheads is $8.60 per direct labour hour.
Budgeted production overhead costs for the year were $473,000 and actual costs incurred were $468,000.
56,000 labour hours were used.
Which ONE of the following statements is correct?

Suggested Answer: C Vote an answer

by Berger at Dec 04, 2025, 09:14 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어