Explain which company you would award the contract to base on the weighted score card in table below.


Suggested Answer:
A weighted score card is a tool with a systematic and a fair process for selecting supplier, based on predetermined criteri a. This tool can help make the decision by presenting a fair display of how all suppliers did in the process. The values of these weights are based on their importance. The supplier with the highest score card is considered the most suitable to be awarded the contract.
In the table above, cost is considered more than all other criteria. Contract length is the lowest which is weighted 2 Base on the weighted score card as presented above, company B scored 78 while company A and company C scored 65 and 63 respectively.
Company A, having scored the highest (78) should be awarded the contract.
*
Refer to the question column for response
In the table above, cost is considered more than all other criteria. Contract length is the lowest which is weighted 2 Base on the weighted score card as presented above, company B scored 78 while company A and company C scored 65 and 63 respectively.
Company A, having scored the highest (78) should be awarded the contract.
*
Refer to the question column for response
by Ryan at Jun 26, 2024, 02:09 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).