Exam L4M3 Topic 5 Question 23 Discussion
Actual exam question for CIPS's L4M3 exam
Question #: 23
Topic #: 5
Question #: 23
Topic #: 5
A procurement professional is preparing a sale & purchase contract of a machinery. Which of the following clauses should be added to the contract? Select TWO that apply
Suggested Answer: B,E Vote an answer
The complexity of the contract will reflect the complexity of the purchase. For simple, low-value purchases, standard terms and conditions may be all that is required, but do not assume that just because the purchase is one-off, the contract will be simple. It may still need to cover the following areas:
- Warranties and guarantees if the one-off purchase has a considerable life-span and is business-critical (e.g., a back-up generator for the office which houses the national computer servers).
- Insurance requirements: including professional indemnity, public/products liability, employer's liability, and cover for any specific risks such as pollution or working at height.
- Specification requirements on quality, timing and delivery
- Minimum quality standards on the business operation (e.g., a catering provider might only be providing sandwiches for a team meeting lunch, but you still need to know its hygiene practices).
- Built-in change process for any goods or services that are beyond very simple (e.g., works contracts always have variations procedures because of the unpredictable nature of such projects).
- Ability to extend the scope of the contract should be minimal or none, and restrained to the single requirement.
- Ability to extend the duration of the contract should be limited to the ability to accommodate unexpected time overruns (which itself should be subject to a damages/penalty provision where they are attributable to the supplier, and an extension to overheads costs where they are attributable to the purchaser).
- Data security protocols need to be considered if personal data is being shared.
Reference:
LO 1, AC 1.3
- Warranties and guarantees if the one-off purchase has a considerable life-span and is business-critical (e.g., a back-up generator for the office which houses the national computer servers).
- Insurance requirements: including professional indemnity, public/products liability, employer's liability, and cover for any specific risks such as pollution or working at height.
- Specification requirements on quality, timing and delivery
- Minimum quality standards on the business operation (e.g., a catering provider might only be providing sandwiches for a team meeting lunch, but you still need to know its hygiene practices).
- Built-in change process for any goods or services that are beyond very simple (e.g., works contracts always have variations procedures because of the unpredictable nature of such projects).
- Ability to extend the scope of the contract should be minimal or none, and restrained to the single requirement.
- Ability to extend the duration of the contract should be limited to the ability to accommodate unexpected time overruns (which itself should be subject to a damages/penalty provision where they are attributable to the supplier, and an extension to overheads costs where they are attributable to the purchaser).
- Data security protocols need to be considered if personal data is being shared.
Reference:
LO 1, AC 1.3
by Baron at Nov 14, 2024, 01:31 PM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).