A project manager reports that the implementation of a new system is on track to be completed under budget
and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of
the following should the project manager do in response to the request?
and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of
the following should the project manager do in response to the request?
Suggested Answer: B Vote an answer
Assess the impact of the request and create a change request. The project manager should assess the impact of
the request and create a change request in response to the stakeholder asking to add mobile device
functionality to a project that is on track to be completed under budget and ahead of schedule. A change
request is a document that formally proposes and records a modification or addition to some aspect of a
project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and
justify the need and rationale for the change and its implications on the project objectives and deliverables. A
change request also helps to initiate the change control process, which involves reviewing, approving,
implementing, and monitoring the change12
the request and create a change request in response to the stakeholder asking to add mobile device
functionality to a project that is on track to be completed under budget and ahead of schedule. A change
request is a document that formally proposes and records a modification or addition to some aspect of a
project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and
justify the need and rationale for the change and its implications on the project objectives and deliverables. A
change request also helps to initiate the change control process, which involves reviewing, approving,
implementing, and monitoring the change12
by Fabian at Aug 11, 2026, 02:25 PM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).