You are the project manager of GHT project. You have planned the risk response process and now you are about to implement various controls. What you should do before relying on any of the controls?

Suggested Answer: A,C Vote an answer

Section: Volume A
Explanation:
Pilot testing and reviewing of performance data to verify operation against design are done before relying on control.
Incorrect Answers:
B: Discovering risk exposure helps in identifying the severity of risk, but it does not play any role in specifying the reliability of control.
D: Articulating risk is the first phase in the risk response process to ensure that information on the true state of exposures and opportunities are made available in a timely manner and to the right people for appropriate response. But it does not play any role in identifying whether any specific control is reliable or not.

by Bonnie at Feb 22, 2024, 07:30 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어