The reason for establishing a stop or freezing point on the design of a new system is to:
Suggested Answer: C Vote an answer
Section: Protection of Information Assets
Explanation:
Projects often have a tendency to expand, especially during the requirements definition phase. This expansion often grows to a point where the originally anticipated cost-benefits are diminished because the cost of the project has increased. When this occurs, it is recommended that the project be stopped or frozen to allow a review of all of the cost- benefits and the payback period.
Explanation:
Projects often have a tendency to expand, especially during the requirements definition phase. This expansion often grows to a point where the originally anticipated cost-benefits are diminished because the cost of the project has increased. When this occurs, it is recommended that the project be stopped or frozen to allow a review of all of the cost- benefits and the payback period.
by Mick at Nov 24, 2024, 11:25 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).