Question #: 1425
Topic #: 2
Which of the following is a continuity plan test that uses actual resources to simulate a system crash to cost-effectively obtain evidence about the plan's effectiveness?

Suggested Answer: C Vote an answer

Explanation/Reference:
Explanation:
A preparedness test is a localized version of a full test, wherein resources are expended in the simulation of a system crash. This test is performed regularly on different aspects of the plan and can be a cost- effective way to gradually obtain evidence about the plan's effectiveness. It also provides a means to improve the plan in increments. A paper test is a walkthrough of the plan, involving major players, who attempt to determine what might happen in a particular type of service disruption in the plan's execution. A paper test usually precedes the preparedness test. A post-test is actually a test phase and is comprised of a group of activities, such as returning all resources to their proper place, disconnecting equipment, returning personnel and deleting all company data from third-party systems. A walkthrough is a test involving a simulated disaster situation that tests the preparedness and understanding of management and staff, rather than the actual resources.

by Abraham at Nov 29, 2024, 03:35 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어