Which of the following disaster recovery/continuity plan components provides the GREATEST assurance of recovery after a disaster?

Suggested Answer: A Vote an answer

The alternate facility should be made available until the original site is restored to provide the greatest assurance of recovery after a disaster. Without this assurance, the plan will not be successful. All other choices ensure prioritization or the execution of the plan.

by Dempsey at Nov 15, 2025, 10:10 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어