Exam PMI-RMP Topic 2 Question 16 Discussion
Actual exam question for PMI's PMI-RMP exam
Question #: 16
Topic #: 2
Question #: 16
Topic #: 2
In the country where a project is being executed, customs procedures are complex and change frequently.
During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?
During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?
Suggested Answer: B Vote an answer
by Erica at Jan 07, 2024, 12:23 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).