Exam PMI-001 Topic 1 Question 614 Discussion
Actual exam question for PMI's PMI-001 exam
Question #: 614
Topic #: 1
Question #: 614
Topic #: 1
You are a project manager for residential construction. As a project manager, you must be especially concerned with building codes-particularly in the plan quality management process. You must ensure that building codes are reflected in your project plans because______________
Suggested Answer: A Vote an answer
During the plan quality management process, the project management team must consider any application area-specific standards, regulations, rules, and guidelines that may affect the project as part of the enterprise environmental factors. Building codes are an example of regulations. [Planning] PMI@, PMBOK@ Guide, 2013, 28-29 and 234
by Burton at Apr 09, 2024, 01:40 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).