Exam PfMP Topic 4 Question 699 Discussion
Actual exam question for PMI's PfMP exam
Question #: 699
Topic #: 4
Question #: 699
Topic #: 4
As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship between the Optimize, Authorize and Provide Oversight processes. What could your advice to him be?
Suggested Answer: A Vote an answer
Explanation
The three mentioned processes are, similar to all processes, recurring in the portfolio life cycle and are not prerequisites to one another. As part of the review meetings, decision may be taken to initiate a component, which requires triggering the authorize portfolio process; on the other hand, decisions to add new components can be taken which requires to optimize the portfolio once again
The three mentioned processes are, similar to all processes, recurring in the portfolio life cycle and are not prerequisites to one another. As part of the review meetings, decision may be taken to initiate a component, which requires triggering the authorize portfolio process; on the other hand, decisions to add new components can be taken which requires to optimize the portfolio once again
by Fitzgerald at Nov 02, 2024, 04:01 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).