Exam PMP Topic 1 Question 896 Discussion
Actual exam question for PMI's PMP exam
Question #: 896
Topic #: 1
Question #: 896
Topic #: 1
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?
How should the facilitator proceed?
Suggested Answer: C Vote an answer
In the context of agile project management, when a facilitator is working with a new team, it is important to establish a common understanding and set the stage for collaboration. Holding a team charter discussion is a foundational step in this process. It allows the team to define their mission, objectives, and the norms that will guide their work together. This session helps in building trust, setting expectations, and ensuring that everyone is aligned with the project's goals. It is a critical step for team formation, especially when the facilitator and the team have not worked together before.
References: The recommendation for an agile facilitator to hold a team charter discussion with a new team is supported by agile best practices and the guidelines provided in PMI's resources on project management and business analysis123
References: The recommendation for an agile facilitator to hold a team charter discussion with a new team is supported by agile best practices and the guidelines provided in PMI's resources on project management and business analysis123
by Francis at Dec 10, 2024, 10:49 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).