Exam PMO-CP Topic 5 Question 41 Discussion
Actual exam question for PMI's PMO-CP exam
Question #: 41
Topic #: 5
Question #: 41
Topic #: 5
A PMO is evaluating its maturity and considering how its evolution impacts organizational effectiveness. The team debates whether increasing the number of functions or transitioning to a more strategic focus defines maturity evolution. When does the evolution of PMO maturity occur?
Suggested Answer: D Vote an answer
PMO maturity evolves as its functions become more sophisticated across all levels-operational, tactical, and strategic. This includes better-defined processes, enhanced stakeholder engagement, and improved value delivery. The focus is on function quality rather than quantity or strategic exclusivity.
References:
* PMI's Organizational Project Management Maturity Model (OPM3).
* The Standard for Project Portfolio Management - Emphasis on functional sophistication.
References:
* PMI's Organizational Project Management Maturity Model (OPM3).
* The Standard for Project Portfolio Management - Emphasis on functional sophistication.
by Lawrence at Dec 14, 2024, 07:51 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).