Exam PMP Topic 2 Question 1107 Discussion
Actual exam question for PMI's PMP exam
Question #: 1107
Topic #: 2
Question #: 1107
Topic #: 2
As you use the critical chain method in lieu of the critical path method in developing your schedule, assume you have determined the buffer schedule activities. Your planned activities are scheduled to their latest possible planed start and end dates. Therefore, you are focusing on______________
Suggested Answer: C Vote an answer
Section: Mix Questions
Explanation:
The purpose of the critical chain method is to modify the project schedule to account for limited resources. The schedule is built using duration estimates with required dependencies and defined constraints as inputs. Then, the critical path is calculated and resource availability is entered, which means there is a resource-limited schedule with an altered critical path. Buffers protect the critical chain from slippage, and the size of each buffer accounts for the uncertainty in the duration of the chain of dependent tasks that lead up to the buffer.
This method then focuses on managing the remaining buffer durations against the remaining duration of task chains.
Explanation:
The purpose of the critical chain method is to modify the project schedule to account for limited resources. The schedule is built using duration estimates with required dependencies and defined constraints as inputs. Then, the critical path is calculated and resource availability is entered, which means there is a resource-limited schedule with an altered critical path. Buffers protect the critical chain from slippage, and the size of each buffer accounts for the uncertainty in the duration of the chain of dependent tasks that lead up to the buffer.
This method then focuses on managing the remaining buffer durations against the remaining duration of task chains.
by Michell at Oct 08, 2025, 05:37 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).