Exam PMI-001 Topic 1 Question 196 Discussion

Actual exam question for PMI's PMI-001 exam
Question #: 196
Topic #: 1
Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?

Suggested Answer: C Vote an answer

This formula assumes that all of the remaining work is independent of the burn rate incurred thus far. AC is $2,900 + [$500 + $1,000]. The $500 is from Activity B, and the $1,000 is from Activity C.
[Monitoring and Controlling] Kerzner 2009, 660 PMI@, PMBOK@ Guide, 2013, 224

by Vincent at Nov 02, 2026, 09:14 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어