Exam PMI-001 Topic 1 Question 196 Discussion
Actual exam question for PMI's PMI-001 exam
Question #: 196
Topic #: 1
Question #: 196
Topic #: 1
Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?


Suggested Answer: C Vote an answer
This formula assumes that all of the remaining work is independent of the burn rate incurred thus far. AC is $2,900 + [$500 + $1,000]. The $500 is from Activity B, and the $1,000 is from Activity C.
[Monitoring and Controlling] Kerzner 2009, 660 PMI@, PMBOK@ Guide, 2013, 224
[Monitoring and Controlling] Kerzner 2009, 660 PMI@, PMBOK@ Guide, 2013, 224
by Vincent at Nov 02, 2026, 09:14 PM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).