Exam PMP Topic 2 Question 117 Discussion
Actual exam question for PMI's PMP exam
Question #: 117
Topic #: 2
Question #: 117
Topic #: 2
Which of the following process is not included in project communication knowledge area?
Suggested Answer: D Vote an answer
Document Project Closure is not a part in Project communication knowledge area.