Which operations can the responsible person perform after a maintenance order is technically completed?
Note: There are 2 correct answers to this question
Note: There are 2 correct answers to this question
Suggested Answer: A,C Vote an answer
After a maintenance order is technically completed, the responsible person can perform the following operations1:
* Lock or unlock the order: This prevents or allows further changes to the order data, such as actual costs, settlement rule, or confirmation data.
* Change the settlement rule: This allows the responsible person to adjust the distribution of costs to the relevant receivers, such as cost centers, assets, or orders.
* Post goods movements: This allows the responsible person to record the consumption or return of materials that were used for the maintenance work.
* Enter measurement documents: This allows the responsible person to record the measurement readings of the technical objects that were maintained.
The responsible person cannot perform the following operations after a maintenance order is technically completed1:
* Update the estimated costs: This is only possible before the order is released or during the execution phase.
* Change the planned costs: This is only possible before the order is released or during the execution phase.
* Change the order type: This is only possible before the order is released.
* Change the order status: This is only possible before the order is technically completed or after it is reversed.
Therefore, the correct answers are A and C. References: 1: Maintenance Order Types | SAP Help Portal
* Lock or unlock the order: This prevents or allows further changes to the order data, such as actual costs, settlement rule, or confirmation data.
* Change the settlement rule: This allows the responsible person to adjust the distribution of costs to the relevant receivers, such as cost centers, assets, or orders.
* Post goods movements: This allows the responsible person to record the consumption or return of materials that were used for the maintenance work.
* Enter measurement documents: This allows the responsible person to record the measurement readings of the technical objects that were maintained.
The responsible person cannot perform the following operations after a maintenance order is technically completed1:
* Update the estimated costs: This is only possible before the order is released or during the execution phase.
* Change the planned costs: This is only possible before the order is released or during the execution phase.
* Change the order type: This is only possible before the order is released.
* Change the order status: This is only possible before the order is technically completed or after it is reversed.
Therefore, the correct answers are A and C. References: 1: Maintenance Order Types | SAP Help Portal
by Faithe at Feb 17, 2025, 02:37 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).