Exam C-TS412-2021 Topic 3 Question 101 Discussion
Actual exam question for SAP's C-TS412-2021 exam
Question #: 101
Topic #: 3
Question #: 101
Topic #: 3
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
Suggested Answer: C,D Vote an answer
Capacity requirements are the demand for capacities that result from planned or actual orders. If a work center is overloaded, it means that its capacity requirements exceed its available capacities. To reduce the overload of the work center, you can trigger automatic capacity leveling inside the project planning board, which is a tool that allows you to plan and monitor capacities for network activities. You can also shift activities backward or forward on the time axis where more capacities are available, which means changing their start and finish dates manually or automatically. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
by Cara at May 06, 2025, 02:29 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).