Exam C-S4CFI-2504 Topic 4 Question 68 Discussion
Actual exam question for SAP's C-S4CFI-2504 exam
Question #: 68
Topic #: 4
Question #: 68
Topic #: 4
In SAP Central Business Configuration, which activities can you perform in the Product-Specific Configuration Phase?
Note: There are 3 correct answers to this question.
Note: There are 3 correct answers to this question.
Suggested Answer: B,C,E Vote an answer
Comprehensive and Detailed in Depth Explanation:
Product-specific configuration in SAP CBC adjusts system settings.
* B: Correct. Sales orgs can be added.
* C: Correct. Billing blocks are configurable.
* E: Correct. Approval thresholds are adjustable.
References: SAP Help Portal - "CBC Product-Specific Configuration."
Product-specific configuration in SAP CBC adjusts system settings.
* B: Correct. Sales orgs can be added.
* C: Correct. Billing blocks are configurable.
* E: Correct. Approval thresholds are adjustable.
References: SAP Help Portal - "CBC Product-Specific Configuration."
by Anna at Sep 07, 2025, 04:46 PM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).