Universal Containers uses Kanban to complete its Salesforce development. In the middle of a sprint, the sales manager submits an important item to the team.
What should the business analyst do next?
What should the business analyst do next?
Suggested Answer: A Vote an answer
Explanation
The business analyst should ask the team to reprioritize the backlog and work on the item at the top. This is because Kanban is a development model that focuses on continuous delivery and flow of work, rather than fixed iterations or sprints. Kanban uses a visual board that shows the status of work items across different stages, such as backlog, in progress, done, etc. Work items are pulled from one stage to another when there is available capacity or demand, rather than according to a predefined schedule or plan. Reprioritizing the backlog can help the team accommodate the new item and ensure that the most important or urgent work is done first.Asking the team to commit to the work for the next sprint may not be a good option because Kanban does not use sprints or time-boxed iterations. Asking the team to pivot and complete the work immediately may not be a good option because it may disrupt the flow of work or create bottlenecks or waste in Kanban.
References:
https://trailhead.salesforce.com/content/learn/modules/salesforce-business-analyst-certification-prep/user-accepta
https://trailhead.salesforce.com/en/content/learn/modules/agile-development-with-scrum
The business analyst should ask the team to reprioritize the backlog and work on the item at the top. This is because Kanban is a development model that focuses on continuous delivery and flow of work, rather than fixed iterations or sprints. Kanban uses a visual board that shows the status of work items across different stages, such as backlog, in progress, done, etc. Work items are pulled from one stage to another when there is available capacity or demand, rather than according to a predefined schedule or plan. Reprioritizing the backlog can help the team accommodate the new item and ensure that the most important or urgent work is done first.Asking the team to commit to the work for the next sprint may not be a good option because Kanban does not use sprints or time-boxed iterations. Asking the team to pivot and complete the work immediately may not be a good option because it may disrupt the flow of work or create bottlenecks or waste in Kanban.
References:
https://trailhead.salesforce.com/content/learn/modules/salesforce-business-analyst-certification-prep/user-accepta
https://trailhead.salesforce.com/en/content/learn/modules/agile-development-with-scrum
by Cash at Dec 12, 2023, 10:37 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).