Exam PSM-II Topic 1 Question 19 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 19
Topic #: 1
How should a Scrum Master respond if the Product Owner plans the first Sprint to only focus on setting up the infrastructure and architecture in order to work on functionality in a subsequent Sprint?

Suggested Answer: A Vote an answer

Getting feedback from the Users and Stakeholders is a crucial activity in Scrum. It reduces waste from building items that add no value. Saying that, the best architectures, requirements, and designs emerge from self- organizing teams.

by Sylvia at Aug 10, 2024, 01:28 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어