Exam PSM-III Topic 1 Question 15 Discussion
Actual exam question for Scrum's PSM-III exam
Question #: 15
Topic #: 1
Question #: 15
Topic #: 1
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities.
Which two activities are part of the Product Owner role according to Scrum?
Which two activities are part of the Product Owner role according to Scrum?
Suggested Answer:
According to Scrum, theProduct Owneris accountable formaximizing the value of the productand for effectiveProduct Backlog management. Two key activities that are explicitly part of this role are:
1. Ordering the Product Backlog to Maximize Value
The Product Owner is responsible forordering the Product Backlogso that the most valuable work is done first. This ordering reflects:
* Business and customer value,
* Risk and uncertainty,
* Strategic goals and learning from previous Sprints.
Through this activity, the Product Owner ensures that the Scrum Team is always working on what matters most.
2. Ensuring Product Backlog Items Are Transparent, Clear, and Understood The Product Owner ensures that Product Backlog Items are:
* Clearly expressed,
* Transparent to the Scrum Team and stakeholders,
* Understood well enough for Developers to select them during Sprint Planning.
This does not mean writing detailed requirements alone, butcollaboratingso that shared understanding exists.
1. Ordering the Product Backlog to Maximize Value
The Product Owner is responsible forordering the Product Backlogso that the most valuable work is done first. This ordering reflects:
* Business and customer value,
* Risk and uncertainty,
* Strategic goals and learning from previous Sprints.
Through this activity, the Product Owner ensures that the Scrum Team is always working on what matters most.
2. Ensuring Product Backlog Items Are Transparent, Clear, and Understood The Product Owner ensures that Product Backlog Items are:
* Clearly expressed,
* Transparent to the Scrum Team and stakeholders,
* Understood well enough for Developers to select them during Sprint Planning.
This does not mean writing detailed requirements alone, butcollaboratingso that shared understanding exists.
by Sandy at Jan 09, 2026, 04:46 AM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).