When does the next Sprint begin?
Suggested Answer: B Vote an answer
The next Sprint begins immediately after the conclusion of the previous Sprint, as stated in the Scrum Guide: "Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint."