What Implementation and Migration element can be used to model sub-projects or tasks within a project, complete projects, programs, or project portfolios?

Suggested Answer: B Vote an answer

Comprehensive and Detailed in Depth Explanation:AWork Packageis anImplementation and Migration element in ArchiMate that represents aseries of actions designed to achieve a specific goal within a defined period. It is used tomodel sub-projects, tasks, projects, and programsas it captures the work needed to realize a specific aspect of an architecture.
TheArchiMate 3.2 Specificationexplicitly defines aWork Packageas an element that structures and organizes the necessary activities within aproject, program, or portfolio.
References:
* Archi User Guide
* ArchiMate 3.2 Specification

by Bruno at Jun 15, 2026, 12:52 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어