Oracle Fusion Project Portfolio Management 2014 Essentials - 1z0-498 Exam Practice Test

Select the option that accurately fills in the blank below.
Function security Privileges in Fusion PPM are also known as______

Correct Answer: C Vote an answer
Project managers typically have the need to plan for granular labor resources, whereas only high-level planning is sufficient for financial purposes. Identify the two true statements about the Project Integration Gateway in this background.

Correct Answer: A,D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Identify two unique characteristics of a business unit in Fusion PPM.

Correct Answer: A,B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Identify three valid values for the pre-seeded Status Indicators in Fusion Project Performance Reporting.

Correct Answer: A,B,C Vote an answer
Select the option that enables the transactions from other sub ledger modules that are imported into Project Costing and are in :Rejected" or "Pending for processing" stage to be viewed.

Correct Answer: B Vote an answer
Select three things the Major Axis on the Project Plan Gantt Chart timescale show when the minor axis is set to Months.

Correct Answer: B,C,E Vote an answer
You have created a Financial Plan type where the planning amount option is set as cost amounts only.Based on this information identify two true scenarios.

Correct Answer: C Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Identify two predefined transaction sources that Fusion PPM uses to import the transactions generated within projects.

Correct Answer: C,D Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어