Microsoft Managing Programs and Projects with Project Server 2013 - 74-344 Exam Practice Test
An organization has performed a portfolio analysis in Project Server 2013 by defining a list of drivers and establishing the prioritization for next year's portfolio.
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: B,D
Vote an answer
You are managing two projects named Proj1 and Proj2. Proj1 has a milestone named Milestone!. Proj2 has a milestone named Milestone2.
You need to create a relationship between both projects that meets the following requirements:
- Milestone2 depends on Milestone1.
- The relationship provides visibility without affecting Milestone2's schedule.
What should you do?
You need to create a relationship between both projects that meets the following requirements:
- Milestone2 depends on Milestone1.
- The relationship provides visibility without affecting Milestone2's schedule.
What should you do?
Correct Answer: D
Vote an answer
Your organization is in the process of deploying Project Server 2013.
Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional and Standard. Your business unit needs to upload and manage the projects in the new platform.
You need to guarantee that the projects are uploaded in an efficient way while maintaining data integrity. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional and Standard. Your business unit needs to upload and manage the projects in the new platform.
You need to guarantee that the projects are uploaded in an efficient way while maintaining data integrity. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: B,D
Vote an answer
You are a project manager for an organization that uses Project Server 2013.
You manage a schedule with a Project Site, which includes a section for documents that team members and other stakeholders need. You have a very large number of documents that you want to put into the Project Site.
You need to upload these documents by using the most efficient method.
What should you do?
You manage a schedule with a Project Site, which includes a section for documents that team members and other stakeholders need. You have a very large number of documents that you want to put into the Project Site.
You need to upload these documents by using the most efficient method.
What should you do?
Correct Answer: D
Vote an answer
You are a program manager for an organization that uses Project Server 2013.
You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it.
You open the master project and realize that these changes are not reflected in the master project schedule.
You need to ensure these changes are reflected in the master project.
What should you do?
You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it.
You open the master project and realize that these changes are not reflected in the master project schedule.
You need to ensure these changes are reflected in the master project.
What should you do?
Correct Answer: D
Vote an answer
You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
Correct Answer: B
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Your organization has implemented Project Server 2013 to plan and control enterprise projects.
Your organization plans to perform a Portfolio Analysis for the first time on the Selection of Projects to be done the next year. Business drivers, as well as a pair wise comparison of those business drivers to set the business priorities, is the chosen method.
Your organization has provided you with a total of 35 business drivers, 30 of which are related in some way.
You need to return with a valid set of drivers and prioritization to perform the analysis.
What should you do?
Your organization plans to perform a Portfolio Analysis for the first time on the Selection of Projects to be done the next year. Business drivers, as well as a pair wise comparison of those business drivers to set the business priorities, is the chosen method.
Your organization has provided you with a total of 35 business drivers, 30 of which are related in some way.
You need to return with a valid set of drivers and prioritization to perform the analysis.
What should you do?
Correct Answer: D
Vote an answer
You are a project manager for an organization that uses Project Server 2013.
You create a complex schedule that has many segments which are divided by your organization's departments and external vendors. The duration of the schedule is 18 months. After six months, you learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize that your schedule has numerous assignments that now may be done by another department. You do not want to delete the assignments because you have many interdependencies among these tasks and the rest of your schedule. However, you cannot have resources working on these tasks at this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to ensure that the team members do not work on or update those tasks.
What should you do?
You create a complex schedule that has many segments which are divided by your organization's departments and external vendors. The duration of the schedule is 18 months. After six months, you learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize that your schedule has numerous assignments that now may be done by another department. You do not want to delete the assignments because you have many interdependencies among these tasks and the rest of your schedule. However, you cannot have resources working on these tasks at this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to ensure that the team members do not work on or update those tasks.
What should you do?
Correct Answer: C
Vote an answer
You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool.
After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change.
You need to solve this problem.
What should you do?
After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change.
You need to solve this problem.
What should you do?
Correct Answer: A
Vote an answer
Your organization uses Project Server 2013. You are the project manager of a schedule.
Team Members send you emails with their percentage complete on their assignments.
Your organization only uses the following two percentages for tracking tasks:
- 50% for tasks that are started
- 100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Team Members send you emails with their percentage complete on their assignments.
Your organization only uses the following two percentages for tracking tasks:
- 50% for tasks that are started
- 100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Correct Answer: C,D