SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C-TPLM22-67 Exam Practice Test

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:

Correct Answer: B Vote an answer
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities?
Please choose the correct answer.
Response:

Correct Answer: B Vote an answer
Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.
Response:

Correct Answer: C Vote an answer
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:

Correct Answer: C,D Vote an answer
What is copied when transferring a simulation version back to an operative project?
There are 3 correct answers to this question.
Response:

Correct Answer: B,C,D Vote an answer
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:

Correct Answer: B Vote an answer
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:

Correct Answer: C Vote an answer
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:

Correct Answer: B,C Vote an answer
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:

Correct Answer: B,E Vote an answer
Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?
Please choose the correct answer.
Response:

Correct Answer: D Vote an answer
For which objects can billing plans be created? (2)

Correct Answer: A,E Vote an answer
Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors?
Please choose the correct answer.
Response:

Correct Answer: C Vote an answer

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어