Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
Correct Answer: B,D,E
Vote an answer
For which objects can billing plans be created? Note: There are 2 correct answers to this question
Correct Answer: A,B
Vote an answer
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However,
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
Correct Answer: A,D
Vote an answer
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
Correct Answer: A,C,D
Vote an answer
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
Correct Answer: A
Vote an answer
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
Correct Answer: A,C