EXIN Agile Scrum Foundation - EX0-008 Exam Practice Test
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
What is the velocity of the team?
Correct Answer: C
Vote an answer
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
What is the elapsed time required to complete the story?
Correct Answer: B
Vote an answer
From which sport is the term "Scrum" and much of the terminology derived?
Correct Answer: A
Vote an answer
Who should update the work estimates during the Sprint?
Correct Answer: B
Vote an answer
Why is planning poker an effective estimation technique?
Correct Answer: C