Please click on the Project Scenario A button to review the project scenario and answer the following question.
MILO DESIGN STUDIO - SHENZHEN, CHINA - PROJECT SCENARIO A
MILO is a small, multi-disciplinary design studio with 30 employees located in Shenzhen, China. Their primary business is interior commercial fit-outs and they also offer sustainability consulting. Three of their employees have achieved their WELL AP credential.
They have recently leased one floor 21,528 ft.a (2 000 m2) in a building owned by another organization to use as their new studio office. This space includes floor to ceiling windows on all four exterior walls. While the windows are numerous, they are also highly tinted, with a visible light transmittance of approximately 0.35 (35%). They intend on installing several living plant walls and have included natural fibers and patterns in their finishings throughout.
Their building is located 984.25 ft. (300 m) from an underground train station and across the road (approx.
328.08 ft. (100 m)) from a large public park. While many employees have indicated that they bike to work on bike trails, the new building's landlord will not allow tenants to use the elevators to bring bicycles to their offices. Instead, their building has bike racks at the building entrance, an underground garage for bike storage, small rentable lockers and basic bike maintenance tools.
MILO considers itself a human-centric design firm and leads with a people-first approach through its employee benefits and organizational policies. As an example, they offer a 50% discount on several mindfulness apps and make guided meditation courses available twice per year to all employees on-site.
PROJECT SCOPE & GOALS
MILO has enrolled their office for WELL Certification to demonstrate their commitment to designing for well-being and employee health. They will be renovating and designing the entire fit-out themselves, including new space configurations that will prioritize natural light.
The space layout will include seating for 45 people in an open-plan office with hot-desking, three conference rooms and four individual phone booths. Additionally, they are planning to update lighting fixtures and purchase new office furniture. MILO do not provide any food or beverages on a daily basis except coffee and tea.
MILO is targeting WELL Certification at the Gold level or higher. This effort is being led by one of their inhouse WELL APs.
How many showers with changing facilities are required for MILO to meet Feature V04: Facilities for Active Occupants?

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A WELL AP is advising a project in achieving Feature W06: Drinking Water Promotion. At minimum, how often should the WELL AP recommend mouthpieces and aerators of water dispensers be cleaned?

Correct Answer: C Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which of the following is an effective strategy to promote stair use by building occupants?

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A WELL AP is creating a pest management plan based upon integrated pest management (IPM) principles.
What is the most effective strategy to minimize the use of pesticides?

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which of the following circumstances would best justify a project team's effort to pursue a greater investment in air purification strategies?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
The owners of a project undergoing WELL Certification want to promote health and wellness. They have created a slide show of each of the WELL features that are achieved by the project, which will run on the screens installed in the lobby. In reviewing the slide-show, the WELL AP notices that a key element is missing.
Which of the following must be determined and included in the slide-show in order to meet the requirements of Feature: C01 Health and Wellness Promotion?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A new employee indicates to the human resources department of a project undergoing WELL Certification that they have a peanut allergy. Due to their role, the employee is required to attend catered meetings within the office for prospective clients. The project is trying to update their catering policy to accommodate the employee's health condition. Which of the following strategies should the WELL AP suggest to meet Feature N09 Special Diets?

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A design for a WELL building has a dry-bulb temperature and relative humidity monitoring system. To achieve Feature T06: Thermal Comfort Monitoring the project team must confirm that

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Occupants of a WELL Certified building are unfamiliar with WELL. Which of the following strategies would best meet Feature C01: Health and Well-being Promotion and promote a greater understanding of the relationship between health and buildings among occupants?
* Develop an educational poster and a partially subsidized online WELL course within the first month of occupancy and annually thereafter

Correct Answer: B Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A permanently installed an conditioner was used during construction What should be done to this equipment prior to occupancy?

Correct Answer: C Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
The production of polychlorinated biphenyls (PCBs) has been widely restricted, as they are

Correct Answer: D Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
As a part of a new initiative of a hospital, the program leader is targeting Feature C11: Civic Engagement.
Which of the following policies should be implemented to support this endeavor?

Correct Answer: A Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어