[Dec 02, 2024] Pass Your C_S4PPM_2021 Dumps Free Latest SAP Practice Tests [Q10-Q35]

Share

[Dec 02, 2024] Pass Your C_S4PPM_2021 Dumps Free Latest SAP Practice Tests

Get Top-Rated SAP C_S4PPM_2021 Exam Dumps Now

NEW QUESTION # 10
Where can you use the BCV report in SAP PPM? NOTE: There are 3 correct answers to this question.

  • A. Metrics
  • B. Review
  • C. Scoring model
  • D. Item
  • E. Bucket

Answer: A,C,E


NEW QUESTION # 11
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required?
NOTE: There are 2 correct answers to this question.

  • A. Value types
  • B. Views
  • C. Cost element groups
  • D. Categories

Answer: B,D


NEW QUESTION # 12
What must you do before you can use multiple currencies in financial planning in portfolio management?

  • A. Define a subnet of currencies in portfolio and project management
  • B. Define a subnet of currencies in project system
  • C. Select multiple currencies in the portfolio item
  • D. Select multiple currencies in the portfolio definition

Answer: B


NEW QUESTION # 13
You review the capacity planning values at bucket level in portfolio management.
Which function can you use to view the items that are assigned to a bucket directly in capacity planning?
Include subobjects

  • A. BCV Reporting
  • B. View Chart
  • C. Distribution

Answer: A


NEW QUESTION # 14
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?

  • A. The Distribution indicator is active role type customizing
  • B. The flexible Assignment indicator is active in role type customizing
  • C. The role has the staffing in preparation status
  • D. The role has the staffing in process status

Answer: C


NEW QUESTION # 15
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question

  • A. Project system project
  • B. Project management projects
  • C. Initiatives
  • D. Standalone items

Answer: C,D


NEW QUESTION # 16
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.

  • A. Role demands
  • B. Relationships between phases
  • C. Duration of tasks
  • D. Relationships between tasks
  • E. Project type

Answer: B,C,D


NEW QUESTION # 17
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?

  • A. The Distribution indicator is active role type customizing
  • B. The flexible Assignment indicator is active in role type customizing
  • C. The role has the staffing in preparation status
  • D. The role has the staffing in process status

Answer: B


NEW QUESTION # 18
What is the priority field in the project definition of a project management project used for?

  • A. To determine the scheduled dates for the project
  • B. To determine the approval authorizations required
  • C. To support the evaluation of projects
  • D. To restrict the selection of project types

Answer: C


NEW QUESTION # 19
How can an existing project management project be integrated with SAP controlling? NOTE: There are
2 correct answers to this question.

  • A. Assign the project roles to an existing internal order manually
  • B. Transfer the project structure element to project system (PS)
  • C. Transfer the project structure element internal orders
  • D. Assign the project definition to an existing PS project definition manually

Answer: B,D


NEW QUESTION # 20
Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question

  • A. 1 year
  • B. 10 days
  • C. 3 months
  • D. 2 weeks

Answer: A,C


NEW QUESTION # 21
Which of the following can you use to create multiple portfolio items simultaneously?

  • A. Item template
  • B. Microsoft Excel import
  • C. Primavera import
  • D. Microsoft project import

Answer: B


NEW QUESTION # 22
You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS? NOTE: There are 3 correct answers to this question

  • A. Documents
  • B. Network components
  • C. WBS elements
  • D. Network activities
  • E. PS texts

Answer: B,C,D


NEW QUESTION # 23
Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question

  • A. Lower-level tasks and checklist are release
  • B. The phase type is set to read-only
  • C. Predecessor phases are assigned the status locked
  • D. Additional tasks cannot be added to the phase

Answer: A,B


NEW QUESTION # 24
When is Bottom-up scheduling mandatory?

  • A. When constraints are used
  • B. When parallel phasing is used
  • C. When summary tasks are used
  • D. When actual time are recorded

Answer: C


NEW QUESTION # 25
Which customizing activity do you use to integrate capacity planning of an item with financial planning?

  • A. Define financial planning settings
  • B. Define financial integration scenarios
  • C. Define portfolio type
  • D. Define financial and capacity views

Answer: B


NEW QUESTION # 26
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?

  • A. BI report
  • B. Evaluation
  • C. Portfolio dashboard
  • D. Business Context Viewer (BCV)

Answer: D


NEW QUESTION # 27
How do you make a decision point field a required field for a specific portfolio item?

  • A. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
  • B. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type
  • C. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
  • D. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type

Answer: C


NEW QUESTION # 28
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question

  • A. The complete phase when Granting Approval indicator
  • B. The completion required indicator
  • C. The approval phase indicator
  • D. The Release Success phase only after Approval indicator

Answer: C,D


NEW QUESTION # 29
Which information can be assigned to a business partner in project management? NOTE: There are 3 correct answers to this question

  • A. Production resources or tools (PRT)
  • B. Work centers
  • C. Personal numbers
  • D. Areas and locations
  • E. SAP users

Answer: B,D,E


NEW QUESTION # 30
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?

  • A. Confirm the task using a completion percentage of less than 100
  • B. Enter an actual finish date of the task in the future
  • C. Set the task status to in process
  • D. Ensure that the Rem. Work manually indicator is inactive

Answer: D


NEW QUESTION # 31
What do you use the check Conflict button for? NOTE: There are 3 correct answers to this question

  • A. Adjustment of work according to resource availability
  • B. Adjustment of dates of staffing
  • C. Adjustment of work according to roles assignment of a task
  • D. Adjustment of dates of roles
  • E. Adjustment of distribution of staffing

Answer: A,D,E


NEW QUESTION # 32
Where can you use stakeholders in portfolio management?

  • A. Bucket
  • B. Item
  • C. Initiative
  • D. Review

Answer: B


NEW QUESTION # 33
You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.
How do you make this selection available?

  • A. Activate the consultant role type
  • B. Assign the consultant role type to the appropriate project type
  • C. Assign the consultant role type to the appropriate item type
  • D. Run a report to enable the consultant role type

Answer: B


NEW QUESTION # 34
A WBS element has been created automatically for a project management project. A change is made to the organizational unit of the project definition.
When is the master data of the internal order updated with the change?

  • A. Upon the next cost planning run
  • B. Upon the next transfer
  • C. Upon release of the WBS element
  • D. Upon release of the project

Answer: B


NEW QUESTION # 35
......

Passing Key To Getting C_S4PPM_2021 Certified Exam Engine PDF: https://www.fast2test.com/C_S4PPM_2021-premium-file.html

C_S4PPM_2021 Exam Dumps Pass with Updated Tests Dumps: https://drive.google.com/open?id=1bSbvPsvm6r2wOnZ9hAKXtb2LNm5EDfqN

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어