Exam Questions Answers Braindumps C-TS412-1909 Exam Dumps PDF Questions
Download Free SAP C-TS412-1909 Real Exam Questions
C-TS412-1909 Exam Certification Details:
| Cut Score: | 51% |
| Languages: | English |
| Exam: | 80 questions |
| Level: | Associate |
| Duration: | 180 mins |
| Sample Questions: | SAP C-TS412-1909 Exam Sample Question |
SAP C-TS412-1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 26
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be changed.
- B. Project versions can be created automatically based on user status.
- C. Manually created project versions always require a project version profile.
- D. Project versions are mandatory for Milestone Trend Analysis (MTA).
Answer: A,D
NEW QUESTION 27
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. To set an actual finish date for WBS elements
- B. To transfer the actual date to the billing plan
- C. To start workflow tasks
- D. For trend analysis
Answer: B,D
NEW QUESTION 28
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.
- A. Network header for activity-account-assigned networks
- B. WBS elements
- C. Network activity for activity-account-assigned networks
- D. Standard WBS elements
Answer: A,B
NEW QUESTION 29
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a service entry sheet
- B. Saving a purchase order
- C. Saving a goods receipt
- D. Saving a supplier invoice
Answer: A,C
NEW QUESTION 30
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.
- A. Create a service entry sheet.
- B. Confirm the activities in the Cross-Application Time Sheet (CATS).
- C. Confirm the network activity for external services.
- D. Post a goods receipt in the goods movement application (MIGO).
Answer: A,B
NEW QUESTION 31
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations can create purchase requisitions.
- B. Multiple project simulations can be used simultaneously.
- C. Project simulations allow posting of actual data.
- D. Project simulations can be used to plan structures and costs.
- E. Project simulations can be created without using an operational project as a template.
Answer: B,D,E
NEW QUESTION 32
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Network activity
- B. BOM item
- C. WBS element
- D. Material master
Answer: A,B
NEW QUESTION 33
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The network profile
- B. The scheduling parameters for the network
- C. The control key
- D. The table of MRP controllers
Answer: B
NEW QUESTION 34
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network profile
- B. Project profile
- C. Parameters for the network type
- D. Network type
Answer: C
NEW QUESTION 35
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The availability check for material components indicates missing parts.
- B. The material is assigned to the activity as a non-stock material.
- C. The material master is set to external procurement.
- D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
Answer: A,D
NEW QUESTION 36
To which object can you assign a factory calendar?
- A. Relationship
- B. Network header
- C. Material component
- D. Milestone
Answer: B
NEW QUESTION 37
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
- B. You can shorten the project mask even when there are existing projects.
- C. You can use the same coding mask for standard projects and operative projects.
- D. You can only use numbers for a project coding mask definition.
Answer: A,C
NEW QUESTION 38
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.
- A. Generate purchase requisition
- B. Stock transfer posting
- C. Generate delivery
- D. Confirm production order
- E. Cancel goods issue
Answer: A,B,C
NEW QUESTION 39
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt into unvaluated project stock
- B. Goods receipt of a non-stock item
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: A,D
NEW QUESTION 40
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. Released WBS elements, activities, and/or activity elements
- B. A header-account-assigned network that is assigned to a sales order item
- C. A dynamic item processor (DIP) profile with the appropriate settings
- D. An activity-account-assigned network that is assigned to a sales order item
Answer: A,C