NEW QUESTION # 33
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
- A. Expenditure Type
- B. Contract Line
- C. Task
- D. Projects
- E. Contract Header
Answer: B,C,D
NEW QUESTION # 34
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)
- A. Project accounting date is the first day of the first open project accounting period.
- B. Project accounting date is the same as the original invoice date.
- C. Accounting date is the same as the original invoice date.
- D. Project accounting date is the last day of the open project accounting period.
- E. Accounting date is the first day of the first open accounting period.
Answer: A,C
NEW QUESTION # 35
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
- A. After the creation of Sub Task 1, Project Start Date would remain unchanged as 01-Jul-2016 and Sub Task 2 would be created with 15-Jun-2016.
- B. After the creation of Sub Task 1, Project Start Date would be changed to 15-Jun-2016 and Sub Task 2 would be created with 15-Jun-2016.
- C. Project Start Date would remain unchanged as 01-Jul-2016 for both actions but the start dates on both subtasks would remain 15-Jun-2016.
- D. After the creation and saving of Sub Task 1, Task Start Date would be changed to 01-Jul-2016 and Sub Task 2 would be created with 01-Jul-2016.
Answer: B
NEW QUESTION # 36
Which two statements are true about a project in "Draft" status?
(Choose two.)
- A. Project managers can view draft projects on the Project Manager Dashboard and use the projects for requirements planning.
- B. Team members cannot see the tasks from draft projects on the Team Member Dashboard or in the My Work area.
- C. Project managers can neither view draft projects on the Project Manager Dashboard nor use the projects for requirements planning.
- D. Team members can see the tasks from draft projects on the Team Member Dashboard or in the My Work area.
Answer: A,B
NEW QUESTION # 37
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
- A. Effort
- B. Remaining Plan
- C. Manual Entry
- D. Cost
Answer: D
NEW QUESTION # 38
Which four notification templates are predefined?
- A. Forgot Password Template
- B. Password Reset Template
- C. Forgot Username Template
- D. New Account Manager Template
- E. New Account Template
Answer: B,C,D,E
NEW QUESTION # 39
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list?
(Choose three.)
- A. All new employees created as persons must have an active assignment.
- B. All new employees created as persons must have an active supervisor.
- C. All new employees created as persons must have an active project role.
- D. All new employees created as persons must be assigned to a department.
- E. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.
Answer: A,D,E
NEW QUESTION # 40
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
- A. USD 134
- B. USD 184
- C. USD 120
- D. USD 70
Answer: D
NEW QUESTION # 41
Which component provides a human workflow service that handles all interactions with users or groups in business processes?
- A. Security Console
- B. BPM Worklist
- C. Subledger Accounting
- D. SOA Suite
Answer: B
NEW QUESTION # 42
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)
- A. If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level.
- B. If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.
- C. If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.
- D. If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.
Answer: A,B
NEW QUESTION # 43
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?
- A. Project Foundation
- B. General Ledger
- C. Subledger Accounting
- D. Project Costing
Answer: A
NEW QUESTION # 44
Which application generates external roles to grant both function and data security? (Choose the best answer.)
- A. Oracle Identity Manager
- B. Business Process Manager
- C. Functional Setup Manager
- D. Authorization Policy Manager
Answer: A
NEW QUESTION # 45
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
- A. Project Manager
- B. Project Accountant
- C. Project Administrator
- D. Project Application Administrator
Answer: C
NEW QUESTION # 46
Which three are true of what you can do in the Project Requirements work area?
- A. Manage your list of backlog items.
- B. Create project tasks for backlog items.
- C. Create an execution project.
- D. Organize backlog items by requirements.
- E. Create an implementation project.
Answer: A,B,D
NEW QUESTION # 47
You cannot generate invoices for a project expenditure item. After running the Generate Invoices program for a billable expenditure item and active contract, the process completes successfully but without any billing, and does not provide any error logs.
The program's processing summary is as follows:
Billing Event Errors 0
Ineligible Contracts 0
Successfully Billing Events Created 0
Ineligible Contract Lines 0
Billing Transaction Exception Errors 0
Ineligible Bill Plans 0
Billing Transaction Exception Warnings 0
Ineligible Associated Projects 0
Successful Billing Transactions 0
Ineligible Expenditure Items 0
Draft Invoice Exception Errors 0
Ineligible Events 0
Draft Invoice Exception Warnings 0
Successful Draft Invoices 0
What was the invoice method classification set to that caused this behavior? (Choose the best answer.)
- A. As Incurred
- B. Percent Complete
- C. Rate Based
- D. Amount Based
Answer: D
NEW QUESTION # 48
Which four standard objects can you configure to include business specific attributes by using Application Composer for Project Execution Management? (Choose four.)
- A. Project Resource Request
- B. Project Issues
- C. Project Gates
- D. Project Milestones
- E. Project Resource Assignment
- F. Project Deliverables
Answer: B,C,D,F
NEW QUESTION # 49
Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?
- A. Manage Project Type page
- B. Manage Capitalized Interest Rates page
- C. Manage Project Plan Type page
- D. Manage Capitalized Interest Rate Schedules page
- E. Manage Expenditure Type page
Answer: A
NEW QUESTION # 50
......