NEW QUESTION 26
You arereviewing the production status of your manufacturing plant shop floor as a production supervisor.
Your production manager wants a report on a work order statuswhich is reserved against a particular customer.
The final assembly of the work order is serialized.
Which option shows the steps to complete the task using the mobile application?
- A. Select the infotile Customer to open the work order details page> Click Actions and select the E-mail icon> Select required work orders>Select the e-mail client, enter the recipient's e-mail, and click Send.
- B. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page > Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and click Send.
- C. Search the work order by customer name to open the work order details page> Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, andclick Send.
- D. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page> Select required work orders> Click Social icon (OSN) > Select recipient, and click Share.
Answer: B
NEW QUESTION 27
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items with some overlap between them in terms of productsmanufactured. The distribution centers stock parts from all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team defines the items and sets the attributes for most parameters. The respective distribution centers and manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.
- A. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Inventory Organization.
- B. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and CorporateEngineering organization as Inventory Organization.
- C. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and Corporate Engineering organization as Item Organization.
- D. Set up Plants as Inventory Organizations, Distribution Centers as Inventory Organizations, and Corporate Engineering organizations as Item Organization.
- E. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Item Organization
Answer: D,E
NEW QUESTION 28
The Cost Accountant has reported to the Production Supervisor that the Work Order transactions are not getting transferred to Costing.
Identify the reason for work order transactions not getting transferred to Costing.
- A. The Costing Interfaced Attribute is enabled in the resource definition.
- B. The item was made inactive after the Work Order transaction.
- C. The Costing Interfaced Attribute is not enabled in the resource definition.
- D. The Manage Item Rules setup is not complete.
Answer: C
NEW QUESTION 29
Identify three types of Item Quantities displayed in the Work Order History tab.
- A. In Process Quantity
- B. Scrapped Quantity
- C. Total Quantity
- D. Remaining Quantity
- E. Completed Quantity
Answer: B,D,E
NEW QUESTION 30
In a Manufacturing Cloud post productionsupport environment, a user wants to update some of the operations in the work orders by using the Midpoint Scheduling feature. However, the user is unable to update any of the orders.
Identify two reasons.
- A. The operations are missing sequence.
- B. None of the operations include scheduled resources.
- C. The work order operations do not have operations start or completion date.
- D. The scheduled resources are not part of the organization selected by the user.
Answer: A,B
NEW QUESTION 31
In what three ways can you set the overcompletion tolerance for a subcomponent yield, so the job order can report the excess production completion?
- A. Overcompletion Tolerance Type = Percentage, value = 100
- B. Overcompletion Tolerance Type = Percentage, value = 0
- C. Overcompletion Tolerance Type = Amount, value > 0
- D. Overcompletion Tolerance Type = Percentage, value > 0
- E. Overcompletion Tolerance Type = Amount,value = 0
Answer: B,D,E
NEW QUESTION 32
In a manufacturing plant, a production operator in a givenshift completes a car assembly and reports this using orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
- A. Resource usage
- B. Scrap material
- C. Material usage
- D. Processing steps
- E. Return material
Answer: A,C
NEW QUESTION 33
Work order costs are computed based on material and resource transactions reported and the cost method of the product. In a manufacturing plant, the production operatorhas completed a work order WO-001 ensuring proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
- A. Transfer Transactions from Production to Costing
- B. Transfer Transactions from Inventory to Costing
- C. Create accounting
- D. Transfer Costs to Cost Management
Answer: A
NEW QUESTION 34
Identify three entities that must be set up in Oracle Manufacturing Cloud to create a Work Definition for an item that will be manufactured in-house.
- A. Manufacturing Lead Time
- B. Operation Items
- C. Production Line
- D. Resources
- E. Operations
Answer: B,D,E
NEW QUESTION 35
A Production Operator needs to load Work Order Transactions from an external system into Manufacturing Cloud.
Identify the correct sequence of tasks to be performed.
- A. Export File to UCM server> Load Data to Fusion repository> Process Import Operations Transactions> Load file from UCM to Interface table.
- B. LoadData to Fusion repository> Export File to UCM server > Process Import Operations Transactions> Load file from UCM to Interface table.
- C. Load Data to Fusion repository> Load File from UCM to Interface table> Export File to UCM server> Process Import Operations Transactions.
- D. Load Data to Fusion repository> Export File to UCM server > Load file from UCM to Interface table
>Process Import Operations Transactions.
Answer: A
NEW QUESTION 36
Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
Identify four REST resources and thecorresponding HTTP action available with Manufacturing Cloud.
- A. Work Order Status POST method
- B. Work Orders GET method
- C. Resource transaction POST method
- D. Work Order Status GET method
- E. Work Orders PATCH method
- F. Resource transaction GET method
Answer: B,C,D,E
NEW QUESTION 37
A Work Center created a month ago is no longer in use now. You want to remove theWork Center; however, the system is no allowing you to delete it.
Identify three reasons for this.
- A. The Work Center is being referenced in the Open Work Order.
- B. The work center is being referenced in the Work Area.
- C. There are resources associated with the Work Center.
- D. The Work Center is being referenced in the Closed Work Order.
- E. The work center is being references in the work definition operation.
Answer: A,B,C
NEW QUESTION 38
A production operator needs to review the materials issued, resources charged, and operations performed for a job that was executed inthe previous shift.
Identify the task the operator has to select to review all the transactions in a single place for both Work Order and Orderless execution.
- A. Manage Work Orders
- B. Review Dispatch List
- C. Report Resource, Material and OperationTransactions
- D. Review Production Transaction History
Answer: A
NEW QUESTION 39
Your customer wants to mass create and modify Work Definitions and the relevant operation, items, and resources available in the spreadsheet.
Which two operations are not supported using ADFDI (Oracle Application Development Framework Desktop Integration)?
- A. Create and update ATO (Assemble To Order) model work definitions
- B. Update Work Definitions
- C. Populate Descriptive flexfields
- D. Create Work Definitions
Answer: A,C
NEW QUESTION 40
A manufacturing cloud user wants to print information available in the work order in PDF.
Identify the three reports that the user can print directly from the work order screen using the Print PDF action.
- A. Print Component List
- B. Bill of material
- C. Resource List
- D. Work Order Traveler
- E. Print Labels
Answer: A,D,E
NEW QUESTION 41
Which entity should you use to configure the manufacturing plant in Functional Manager?
- A. Plant
- B. Organization
- C. Legal Entity
- D. Business Unit
Answer: A
NEW QUESTION 42
TheManufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day andNight Shift.
Identify the correct sequence of steps to achieve this requirement.
- A. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column> Enter 2 in Night Shift Column
- B. Associate Resource R2 with Work Center WC1> Select Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
- C. Associate Resource R2 with Work Center WC1> Select the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column > Enter 2 in Night Shift Column.
- D. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
Answer: C
NEW QUESTION 43
An employee is responsible for dealing with different manufacturing practices and processes, machines, tools and equipment that turn raw material into a product.
Which seeded job role must this employee be provided with?
- A. Production Engineer
- B. Production Operator
- C. Manufacturing Supervisor
- D. Manufacturing Engineer
- E. Production Supervisor
Answer: D
NEW QUESTION 44
Identify thetwo capabilities that the Application Development Framework Desktop Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.
- A. You can mass create and update work definitions and their operations only and cannot add items and resources in work definitions.
- B. You can mass create and update work definitions and their operations, items, and resources.
- C. You can mass create and update work definitions and their operations, items only and cannot add resources in work definitions.
- D. You can copy work definitions form one organization to another organization.
Answer: B,D
NEW QUESTION 45
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the MorningShift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?
- A. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
- B. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 40% against the resource LATHE in the Evening Shift column.
- C. Select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.
- D. Do not select the Available24 Hours check box and in the Resource Availability region, enter 60% against the resource LATHE in the Morning Shift column.
- E. Select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
- F. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.
Answer: C,D
NEW QUESTION 46
In your customer's manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its supplies formthe Warehouse subinventory through automatically created Movement Requests.
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?
- A. Replenishment Requests
- B. Batch Wave Movement Requests
- C. Requisition Movement Requests
- D. Pick Wave MovementRequests
Answer: C
NEW QUESTION 47
A Production operator in your company is required to report production activities, suchas completing or scrapping production units, by referencing a work definition without creating work orders.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
- A. Orderless Transactions
- B. Resource Transactions
- C. Material Transactions
- D. Operation Transactions
- E. Movement request
Answer: A
NEW QUESTION 48
Identify four parameters that are considered in the calculation of manufacturing lead time in Oracle Manufacturing Cloud.
- A. The lot size of the item
- B. Resource calendar exceptions
- C. Resource calendars of the work centers involved
- D. The primary work definition of the item
- E. The shifts are defined in the plant calendar
- F. Plant calendar exceptions
Answer: A,B,D,E
NEW QUESTION 49
A customer has a distribution warehouse (DW) for After Sales and Service and an in-house manufacturing plant (MP). Sales orders are created and shipped from DW.
Identify the two Sourcing Rules that need to be set for order promising to schedule the order.
- A. Define Local sourcing rule for organization MP: Source Type Transfer To, Source DW
- B. Define Local sourcing rule for organization MP: Source Type Make At, Source MP
- C. Define Local sourcing rule for organization DW: Source Type Transfer From, Source MP
- D. Define Local sourcing rule for organization DW: Source Type Make From, Source MP
Answer: B,C
NEW QUESTION 50
......
Fast2test 1z0-1075-22 Exam Practice Test Questions: https://www.fast2test.com/1z0-1075-22-premium-file.html