NEW QUESTION 18
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.
- A. 1 and 4
- B. 1 and 2
- C. 3 and 4
- D. 2 and 3
Answer: C
NEW QUESTION 19
Which statement about the 'embrace change' target is CORRECT?
- A. It reduces testing in order to meet deadlines
- B. It encourages the customer to raise new ideas
- C. It reduces the planning of dependencies between projects
- D. It minimizes the time needed to train a new team member
Answer: B
NEW QUESTION 20
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 21
What should be decided when configuring PRINCE2 effectively?
- A. Which areas are not enabled to work with agile
- B. Where to put the emphasis and where to add guidance
- C. What to remove and where to add guidance
- D. What to significantly change to create the right blend
Answer: D
NEW QUESTION 22
During which process should release planning be done for the FIRST time?
- A. Controlling a stage
- B. Managing a stage boundary
- C. Managing product delivery
- D. Initiating a project
Answer: B
NEW QUESTION 23
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- A. It enables team dynamics to remain the same
- B. It sets the project baseline at the correct level
- C. It reduces testing in order to meet deadlines
- D. It improves the supplier's reputation with the customer
Answer: C
NEW QUESTION 24
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should attend regular project progress meetings
- B. The project board should make decisions based on the Agilometer risks
- C. A project board member should fulfill the product owner role within a delivery team
- D. The project board should increase the stage-level time tolerance
Answer: C
NEW QUESTION 25
Which is a reason for releasing a product into a staging area?
- A. It enables the faster delivery of changes
- B. It enables a phased Waterfall approach
- C. It supports management by exception
- D. It supports regulatory compliance checking
Answer: D
Explanation:
Reference:
%20and%20verification%20process
NEW QUESTION 26
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To use empiricism, based on knowledge that comes from experience
Answer: D
NEW QUESTION 27
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It states that deadlines should not be moved
- C. It promotes the use of experiments carried out in a scientific way
- D. It has distinct goals for each stage of development
Answer: D
NEW QUESTION 28
Which is often used during a retrospective to capture lessons?
- A. A Glad! Sad! Mad! board
- B. A burn chart
- C. A Kanban board
- D. A Gantt chart
Answer: A
NEW QUESTION 29
Which is a purpose of the 'controlling stage' process?
- A. To establish whether the project is complete
- B. To draft the plan for the next stage's work
- C. To report stage progress to the project board
- D. To execute and deliver the project product
Answer: C
Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control
NEW QUESTION 30
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?
- A. Tailor to suit the project
- B. Continued business justification
- C. Learn from experience
- D. Defined roles and responsibilities
Answer: D
NEW QUESTION 31
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance can be fixed and flexed
- B. Cost tolerance is fixed
- C. Cost tolerance can be fixed or flexed
- D. Cost tolerance is flexed
Answer: D
NEW QUESTION 32
What information is NOT typically displayed on a burn chart?
- A. Amount of time elapsed
- B. Definition of 'ready'
- C. Effort remaining
- D. Actual amount of work done
Answer: B
NEW QUESTION 33
What is the definition of a timebox?
- A. A regular event that looks at how processes can be improved
- B. A description of the rate of progress a team is making
- C. A period where work is carried out to achieve a goal
- D. A tool to write a requirement in the form of who, what and why
Answer: C
NEW QUESTION 34
What should the business case state about the minimum viable product (MVP)?
- A. What the MVP is
- B. When the MVP will be defined
- C. That the MVP is the same as project viability
- D. That the MVP must go into operational use
Answer: D
NEW QUESTION 35
Which process can take place during a release review workshop?
- A. Controlling a stage
- B. Directing a project
- C. Managing product delivery
- D. Managing a stage boundary
Answer: C
NEW QUESTION 36
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
- A. Typical
- B. Preferable
- C. Effective
Answer: C
NEW QUESTION 37
Which role is responsible for facilitating the Agilometer assessment?
- A. Team manager
- B. Project board
- C. Customer subject matter expert
- D. Project manager
Answer: D
NEW QUESTION 38
......