Valid C-TS422-1909 Exam Q&A PDF C-TS422-1909 Dump is Ready (Updated 91 Questions)
Exam Questions and Answers for C-TS422-1909 Study Guide
NEW QUESTION 41
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?
- A. Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
- B. Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.
- C. Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
- D. Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator
Answer: B
NEW QUESTION 42
A planner updated a production order status from partially confirmed "PCNF" to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:
- A. The warehouse clerk still carry out goods issue transactions
- B. The production operator cannot enter additional confirmations
- C. The production manager can still see the capacity requirements
- D. The buyer can still see component reservations
Answer: B
NEW QUESTION 43
A material has been set up as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?
- A. Change the phantom item indicator for the phantom assembly in the BOM.
- B. Change the special procurement key of the phantom assembly in the BOM.
- C. Change the item category of the phantom assembly in the BOM.
- D. Change the explosion type of the phantom assembly in the BOM.
Answer: D
NEW QUESTION 44
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning?
There are 2 correct answers to this question.
Response:
- A. Work center
- B. Material master
- C. Contract
- D. Production plant
Answer: C,D
NEW QUESTION 45
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Manual planning without check
- B. Consumption-based planning
- C. Forecast planning
- D. Material requirements planning
Answer: B
NEW QUESTION 46
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
- A. Production scheduling profile
- B. Scheduling margin key
- C. Confirmation profile
- D. Operation control key
Answer: A,D
NEW QUESTION 47
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created?
Please choose the correct answer.
Response:
- A. Costs
- B. Quota arrangement
- C. Delivery date
- D. Component availability
- E. Vendor rating
Answer: B
NEW QUESTION 48
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
- A. Use batch determination.
- B. Use the material where-used report.
- C. Use the material staging report.
- D. Use the batch information cockpit.
Answer: D
NEW QUESTION 49
In which data object is the production line (Repetitive manufacturing relevant work center) maintained?
Please choose the correct answer.
Response:
- A. Bill of material
- B. Production version
- C. Cost collector
- D. Repetitive manufacturing profile
Answer: B
NEW QUESTION 50
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work Center BOM
- B. Sales Order BOM
- C. Functional Location BOM
- D. Class BOM
Answer: B,C
NEW QUESTION 51
In which data objects do you maintain the production line as the work center for repetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Production version
- B. Repetitive manufacturing profile
- C. Routing
- D. Production cost collector
Answer: A,C
NEW QUESTION 52
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Work center hierarchy
- B. Operation network
- C. Resource network
- D. Setup matrix
Answer: A
NEW QUESTION 53
You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
- A. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
- B. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.
- C. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
- D. The previously dispatched operation stays as is the new operation is inserted after the dispatched operation.
Answer: A
NEW QUESTION 54
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.
- A. Checking control must have an overall profile assigned in customizing.
- B. Indicator Relevant for finite scheduling must be set.
- C. PRT Availability check must be set.
- D. Checking rule and group must be assigned.
Answer: A,B
NEW QUESTION 55
You are using the document management system (DMS) . Where should the DMS document links be assigned, to have them automatically copied to production orders?
There are 2 correct answers to this question.
Response:
- A. Work center
- B. Routing header
- C. Bill of material
- D. Material master
Answer: C,D
NEW QUESTION 56
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
- A. Infinite resource and infinite strategy
- B. Infinite resource and finite strategy
- C. Finite resource and infinite strategy
- D. Finite resource and finite strategy
Answer: D
NEW QUESTION 57
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
- A. Minimum lot sizing
- B. Fixed lot sizing
- C. Exact lot sizing
- D. Periodic lot sizing
Answer: D
NEW QUESTION 58
......